B200 nodes are out of waitlist in DFW-1
Hardware
The second tranche of HGX B200 landed on 19 August, burned in for a week, and cleared the waitlist this morning. Eight 8-way nodes are live, two more racks are on order for IAD-1 with a target of November. Power is the constraint, not supply: a B200 node draws ~10.2 kW at the wall and we had to add a 415 V busway to cage 4 for them.
Single-GPU B200 instances are not something we can offer — the parts only exist on an 8-way baseboard — so the smallest unit is 2× (a half-node, NVLink-partitioned) at $7,391/mo, which is two cards at $3,890 less the 5% two-GPU discount. Live stock per region sits on the B200 rental page.